Home NEWS NNPCL boss, Kyari reveals when Kaduna refinery will begin production

NNPCL boss, Kyari reveals when Kaduna refinery will begin production

0

Mele Kyari, the Group Managing Director of the Nigerian National Petroleum Company Limited, NNPCL has made a promise to Nigerians.

He stated that the refinery in Kaduna State will be ready for production by December 2024.

He disclosed this during a meeting with the Independent Petroleum Marketers Association of Nigeria and the Major Energy Marketers Association of Nigeria in Abuja.

He disclosed that operations at the Port Harcourt refinery are scheduled to begin in two weeks.

According to Kyari: “We did a mechanical completion of the (Port Harcourt) refinery, that was what we said in December. We now have crude oil already stocked in the refinery. We are doing regulatory compliance tests that must happen in every refinery before you start it, and I assure you that this Port Harcourt refinery will start in the next two weeks.

“Completing the mechanical work means that you are done with the rehabilitation work, now you have to test to see how it works. Of course, we have also completed the mechanical work on the Warri refinery.

“It is also undergoing regulatory compliance; processes that we are doing with our regulator, and this will soon be completed and it will be ready.

“The Kaduna refinery will be ready by December. We have not reached that stage in Kaduna, but we promise Kaduna will be delivered by December.”

GET IT NOW

LEAVE A REPLY

Please enter your comment!
Please enter your name here